Progress Report

Since I last wrote, some progress has been made at the two nearby construction sites, but it has been very sporadic. As shown in the photo below, the piers and foundation at 204 N. Bayview do follow the shape predicted by the trenches shown in this post, but I could have taken the same photo last week or perhaps the week before.

As for the house rising at 112 N. Summit, some sheathing and a roof/second story have been added since September 7, but all the work occurred in one- and two-day spurts, with no sign of activity between.

There is no obvious reason for the delay: the weather has been generally fair and rather pleasant. Perhaps these jobs are the contractors’ stepchildren.