Bluff Neighborhood Construction Report 2-5-17

Very little to report this week, I’m afraid.

252 N. Bayview Street

Move-in has definitely begun. Although it doesn’t appear the owners are yet in residence, many furnishings (including a grand piano) have been moved into the downstairs rooms. This shot through the south side door shows new hanging light fixtures over the kitchen island.

Exterior work is also complete except for some painting.

Here’s a close-up of the balcony with the corrected posts.

These stepping stones from the carport to the back of the house are (relatively) new, I think.

352 N. Summit Street

What appeared to be a husband-and-wife team were at work both Saturday and Sunday. Saturday they were working on the tile in the master bathroom shower.

351 N. Summit Street

No apparent change outside. Inside, a detail I hadn’t previously noticed. Looking through one of the windows, I saw what looked like a brick floor in the foyer. Although this shot through the glass in the front door doesn’t show the floor clearly, what at first appeared to be bricks are actually blocks of wood laid in a diagonal pattern.

120 Kiefer Avenue

The steps have been completed and look very nice. Puzzlingly, the dumpster is gone, so perhaps work on the main house is not in progress after all.

59 N. Summit Street

Work seems to have resumed here. I’ll have a further report next week.

Advertisement
This entry was posted in Construction. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s