Monthly Archives: February 2017

Bluff Neighborhood Construction Report 2-26-17

Very little to report today, I’m afraid. 352 N. Summit Street The staircase has been finished. The space I identified as a “linen closet” in the hall bath upstairs now has this built-in. Aside from those two changes, I could … Continue reading

Posted in Construction | Leave a comment

Bluff Neighborhood Construction Report 2-19-17

Lots of interesting new developments this week! 352 N. Summit Street The big story this week is cabinetry, but I’ll start with this photo that you may be able, with difficulty, to make out as the still-boxed stone hearth. It … Continue reading

Posted in Construction | Leave a comment

Bluff Neighborhood Construction Report 2-12-17

In which we bid farewell to one project but touch base on several others. 252 N. Bayview Street The porch railing has been painted, the unwanted/unneeded railing on the steps has been removed, and there is a car in the … Continue reading

Posted in Construction | Leave a comment

Bluff Neighborhood Construction Report 2-5-17

Very little to report this week, I’m afraid. 252 N. Bayview Street Move-in has definitely begun. Although it doesn’t appear the owners are yet in residence, many furnishings (including a grand piano) have been moved into the downstairs rooms. This … Continue reading

Posted in Construction | Leave a comment